Master Systems Inc. - Client Successes Excerpts
ROI on Improvement

Project Results by SEI Level

SEI Level

Calendar Time (Months)

Effort (Person Months)

Total Cost ($000)
(Median)
(Lowest)
(Highest)
I
29.8
593.5
5,440
1,786
101,721
II
18.5
143.0
1,311
962
1,732
III
15.2
79.5
728
518
933
IV
12.5
42.8
392
279
502

For the code and test phases only
of a typical 200,000-line business application.

Project Results by SEI Level

(cont.)

SEI Level

Calendar Time (Months)

Effort (Person Months)

Defects
Total Cost US $000 (Median)
Discovered
Shipped
I
29.8
593.5
1,348
61
5,440
II
18.5
143.0
328
12
1,311
III
15.2
79.5
182
7
728
IV
12.5
42.8
97
5
392

Defect counts include all phases up to final customer shipment.

All contents © copyright Master Systems Inc. Please respect the copyright.
If you reprint or republish the table please be sure to include the copyright notice.
To download more information about this table and its derivation, please click here.


 

Master Systems Inc. - Client Successes Excerpts

Client Successes:

Two clients win Wall St. & Technology CIO of the Year...

Architecture combined with Product Marketing & project management...

Revenue & net income increased N-fold, with level employment...

read more