Project Results by SEI Level
|
|
Calendar Time (Months)
|
|
Total Cost ($000)
|
|
(Median)
|
(Lowest)
|
(Highest)
|
|
I
|
29.8
|
593.5
|
5,440
|
1,786
|
101,721
|
|
II
|
18.5
|
143.0
|
1,311
|
962
|
1,732
|
|
III
|
15.2
|
79.5
|
728
|
518
|
933
|
|
IV
|
12.5
|
42.8
|
392
|
279
|
502
|
For the code and test phases only
of a typical 200,000-line business application.
Project Results by SEI Level
(cont.)
|
|
Calendar Time (Months)
|
|
Defects
|
Total Cost US $000 (Median)
|
| Discovered |
Shipped
|
|
I
|
29.8
|
593.5
|
1,348
|
61
|
5,440
|
|
II
|
18.5
|
143.0
|
328
|
12
|
1,311
|
|
III
|
15.2
|
79.5
|
182
|
7
|
728
|
|
IV
|
12.5
|
42.8
|
97
|
5
|
392
|
Defect counts include all phases up to final customer
shipment.
All contents © copyright Master Systems Inc. Please respect
the copyright.
If you reprint or republish the table please be sure to include the copyright
notice.
To download more information about this table and its derivation, please
click here.
|
Master Systems Inc. - Client Successes Excerpts
Client Successes:
Two clients win Wall St. & Technology CIO of the Year...
Architecture combined with Product Marketing & project management...
Revenue & net income increased N-fold, with level employment...
read more
|